Jurong East EC launch timeline

Nothing is on sale yet, and won’t be before 2028. Here’s what happens and roughly when. Dates after the land award are my estimates, based on how other ECs went.

Last updated 15 Oct 2026.

  1. 1 Oct 2026

    Canberra Drive EC: 13 bids and a record land priceThe first EC site sold under the new rules drew a top bid of about $825 psf ppr. Developers will look at this when they bid for Jurong East.

  2. Dec 2026estimatenow

    HDB opens the Jurong East Avenue 1 tenderAbout 735 units on a 99-year lease. The tender is usually open for around three months.

  3. 2027estimate

    Tender closes and HDB awards the siteHDB announces the winning developer and the land price on the same day.

  4. 2027 to 2028estimate

    Design, approvals, showflatThe developer designs the project. The site plan, unit mix and floor plans come out during this period.

  5. 2028estimate

    E-application and bookingThis is when your income is checked. First-timers get 90% of the units for the first two years.

  6. About 2031estimate

    TOP, and the 10-year MOP startsYou can sell to citizens and PRs from about 2041, and to anyone from about 2046.

Tender timing from the HDB Government Land Sales page. Later dates assume the usual 12 to 18 months from award to launch, and about three years to build.

How the EC launch works

E-application

When the developer launches, there’s an e-application window of one to two weeks, usually around the showflat preview. You submit your household details, and this is when your income, citizenship and property ownership are checked.

Ballot and booking

Everyone who applied is balloted into a queue to choose units. Here, 90% of units are kept for first-timer families for the first two years. Second-timers choose from the other 10%, and there’s another ballot for them two years after launch if units are left.

Booking and payments

When you book, you pay 5% in cash for the Option to Purchase. The Sale and Purchase Agreement follows a few weeks later, with the rest of the 25% downpayment. After that, the bank loan pays out in stages as the building goes up. There’s no Deferred Payment Scheme here.

What the dates mean for you

First-timers

Your income is checked when you apply in 2028, not now. If you’re close to $18,000 a month, keep that in mind. Try to keep enough in your CPF Ordinary Account for the downpayment.

HDB upgraders

Your flat must have finished its MOP before you apply, and you must sell it within six months of the EC’s TOP (around 2031). Many upgraders stay in their flat until then, so they only move once.

Private owners

The 30 months are counted back from the day you apply. If your sale completed by late 2025, you’re clear for a 2028 application. Later than that, you may not be.

Check your eligibility

Want to be told when things happen?

I update this site when HDB opens the tender, when the bids come out, when the land is awarded and when the developer names the project. WhatsApp me and tell me which ones you want, and I’ll message you.

Keep me posted

See all updates

Not sure about timing?

When to sell your flat, whether to wait for the second-timer ballot, how the 30 months are counted. WhatsApp me and I’ll go through it with you.

Jeffery Ng · CEA Reg. No. R050136D · Huttons Asia Pte Ltd · Licence No. L3008899K

Chat with us today!

I reply on WhatsApp

Timeline questions

When is the Jurong East EC tender?

HDB should open the tender for the Jurong East Avenue 1 site in December 2026. The exact date goes up on HDB’s GLS page when it opens.

When will the Jurong East EC showflat open?

Not until the developer is chosen in 2027 and gets its approvals. For recent ECs, the showflat opened about 12 to 18 months after the land was sold.

How does the EC e-application and ballot work?

You submit an e-application during a window of one to two weeks. Everyone is then balloted, and you book a unit in your ballot order. Here, 90% of units are kept for first-timer families for the first two years. Second-timers pick from the other 10% and get another ballot two years after launch.

When is the expected TOP for Jurong East EC?

Around 2031, if it launches in 2028 and takes the usual three years to build. The 10-year MOP starts from TOP.

How will I know when something changes?

I update the Updates page whenever something happens. If you WhatsApp me, I will message you about the things you want to know, like the tender or the launch date.